Title: BPMN:pools appaer under collaboration? why?
Post by: Jüri on September 08, 2014, 06:11:50 pm
Hi!

using version 11.1.1111
all pools created on businessprocess diagram are placed under collaborationmodel, why is this?

I created BPMN 2.0 businessprocess diagram.
placed businessprocess element on it.
opened created businessprocess (diagram)
added pool to the diagram.
as a result, EA created automatically CollaborationModel element in project browser and placed created pool under it. why is this? can I avoid that happening?
I would expect to have all businessprocess elements that I create listed under business process element they belong to.

any suggestions how to avoid that?

Thanks!
Title: Re: BPMN:pools appaer under collaboration? why?
Post by: Eve on September 09, 2014, 09:31:27 am
It's that way to follow the BPMN specification. Pools are Participants and Participants must be owned by a collaboration.

A Pool can be shown on a Process diagram, but the Pool is still owned by a collaboration. If you have your diagram under a Process element EA build 1111 will help you to create that situation too.