Sparx Systems Forum

Enterprise Architect => General Board => Topic started by: dillon042603 on May 17, 2011, 07:23:12 am

Title: Copy Activity Diagrams Across Projects
Post by: dillon042603 on May 17, 2011, 07:23:12 am
I know how to copy diagrams across projects in EA, but I would like to know if there is a way to do this without bringing all of the traceability/realization with it?  If for any reason this isn't possible and I delete the traceability off of the new project that I just pasted the diagrams in, will it remove the traceability from the original project?

Thanks,

Jen
Title: Re: Copy Activity Diagrams Across Projects
Post by: Bill McCracken on May 18, 2011, 02:50:52 am
You can export it, then re-import it.  I've done this with no problems.