Enterprise Architect => Automation Interface, Add-Ins and Tools => Topic started by: Martin Lichtin on August 25, 2011, 07:00:38 pm

Title: BPMN 2.0 process - how to create a sub-process?
Post by: Martin Lichtin on August 25, 2011, 07:00:38 pm
Can't figure out how to create a sub-process.. How is it done?
I'd expect a Task/Activity with a + sign it which I could click
to extend and edit its contents (or similar).
Title: Re: BPMN 2.0 process - how to create a sub-process
Post by: philchudley on August 26, 2011, 04:02:36 am
Right-click and select Advanced | Make Composite  - this creates a linked BPMN Business Process diagram and displays the + sign

You may also change the TaggedValue activityType to Sub-process

Please note that in order to create a linked BPMN process diagram, you must make the activity a composite, just setting the tagged value merely displays the +

Cheers

Phil