Add, Modify and Delete Tasks
This topic explains how to maintain project tasks.
Access Project | Project Status > Tasks
Project | Calendar > Project Tasks mode
Use to
• | Add project tasks |
• | Edit project tasks |
• | Delete project tasks |
How to
To maintain tasks
Step |
Action |
See also |
||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 |
If creating a new task:
If editing an existing item:
The Task Detail dialog displays.
|
|
||||||||||||||||||||||||||
2 |
Enter or update the following details of the task, selecting a value from the field's drop-down list where appropriate:
|
|
||||||||||||||||||||||||||
3 |
Click on the Apply button.
|
|
||||||||||||||||||||||||||
4 |
To create another entry click on the New button or, to close, click on the OK button.
|
|
||||||||||||||||||||||||||
5 |
To delete a task:
|
|
Notes
• | Owner and Assigned fields are filled from the Project Authors, Resources and Project Clients |