Please note : This help page is not for the latest version of Enterprise Architect. The latest help can be found here.
Resource View
The Resource view shows the current commitments of each allocated resource in the project as a list of allocation records and a Gantt chart of the progress of the allocations.
The display initially shows the resources and their overall commitment; click on the 'plus-box' to the left of the name of the resource to expand the entry to show the elements and the allocation period for each element.
The display shows both complete allocations and those that are still in progress; an internal filter hides completed allocations two weeks after the end date, and incomplete allocations one month after the end date. Tasks you can perform include checking the:
• | Dates on which specific resources or all resources are currently allocated |
• | Elements to which each resource is allocated |
• | Dates on which a resource is allocated to work on a specific element |
• | General progress of the resource in completing the work |
• | Specific details of the allocation of a resource to an element and task or role |
Access Project | Project Gantt View > Resource View
Resource View options
Option |
Usage |
See also |
||||||
---|---|---|---|---|---|---|---|---|
Filter the display by task allocation |
Right-click on the list and select the Show Filter Bar context menu option. To hide the Filter Bar again, right-click and select the Hide Filter Bar option. The Filter Bar displays at the top of the columns; type in a text string to filter for element names, element status, role or task names, or percentage-completeness, beginning with the text or digits. You can use the Tab key to move across the fields. Having set a filter value, you can edit it either by clicking on it or by right-clicking and selecting the Edit Filter option. To delete the value altogether, click on the blue cross at the right of the field.
|
|||||||
Filter the display by Start or Completion date
|
The display default is to show current tasks for which the end date has not. Right-click on the list and select one of the three context menu options:
|
|
||||||
Display the properties of the element to which the resource is assigned
|
Right-click on the entry and select the Show Element Properties context menu option. The Properties dialog for the element displays.
|
|||||||
Display the resource allocation details |
Right-click on the entry and select the Show Task Properties context menu option. The Assigned Resources dialog displays; you can edit the details and, if necessary, change the resource allocated to the element.
|
|||||||
Refresh the report |
Right-click on the entry and select the Refresh context menu option. The content of the display is refreshed and collapsed to resource level.
|
|
||||||
Display the Resource Allocation records for the element |
Right-click on the entry and select either of the context menu options:
The Project Management window displays at the Resource Allocation tab, with the details of the selected entry shown in the fields and the other resource allocations for the element listed in the left-hand panel. You can edit the details and, if necessary, change the resource allocated to the element.
|
|||||||
Reposition the Gantt chart to show the start date or end date of an allocation, or today's date |
Right-click on the entry and select the required option:
The display shifts to put the required date in the center of the chart.
|
|
||||||
Locate the element in the Project Browser |
Right-click on the element name and select the Find in Project Browser context menu option. The area of the Project Browser containing the element is brought into focus and expanded, and the element is highlighted.
|
|
||||||
Save an image of the Gantt chart to file |
Right-click on the tab and select the Save Image to File context menu. option The Save As Image dialog displays, on which you specify the file name, location and graphics file type to save to.
|
|
||||||
Save an image of the Gantt chart to the clipboard |
Right-click on the tab and select the Copy Image to Clipboard context menu option. You can paste the image from the clipboard into your preferred graphics package.
|
|
Learn more