Please note : This help page is not for the latest version of Enterprise Architect. The latest help can be found here.
Add, Modify and Delete Tasks
This topic explains how to add, edit and delete project tasks.
Access Project | Project Status > Tasks
Project | Calendar > Project Tasks mode
Maintain Tasks
Step |
Action |
See also |
||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
1 |
If creating a new task:
If editing an existing item:
The Task Detail dialog displays.
|
|
||||||||||||||||||||||||||
2 |
Enter or update the following details of the task, selecting a value from the field's drop-down list where appropriate:
|
|
||||||||||||||||||||||||||
3 |
Click on the Apply button.
|
|
||||||||||||||||||||||||||
4 |
To create another entry click on the New button or, to close, click on the OK button.
|
|
||||||||||||||||||||||||||
5 |
To delete a task:
|
|
Notes
· | Owner and Assigned fields are filled from the Project Authors, Resources and Project Clients |
Learn more
The material ("material" includes all pages, documents and on-line graphics) on this web site is protected by copyright law. (C) 1998-2015 Sparx Systems Pty Ltd.