setting priority to tasks in BPMN?
« on: January 26, 2013, 09:03:28 pm »
I have to model a process in which there several task that should be done in a regular interval time.and they have different priority, the more important, the sooner, while this tasks are not always sequentialy, one after the other.
i would appreciate it if you could introduce me some example model.

with regards
BJ

OpenIT Solutions

  • EA User
  • **
  • Posts: 555
  • Karma: +9/-1
    • View Profile
Re: setting priority to tasks in BPMN?
« Reply #1 on: January 30, 2013, 01:22:35 am »
It sounds like what you may need to look at / think about is a Timer start or intermediate event in combination with a parallel or inclusive gateway.

There is a taskPriority tagged value, but without the above, i don't think it would serve your purpose.

Regards,

Jon.