Book a Demo

Author Topic: Get All Latest is extremely long - EA 9 build 906  (Read 3031 times)

q2

  • EA Novice
  • *
  • Posts: 19
  • Karma: +0/-0
    • View Profile
Get All Latest is extremely long - EA 9 build 906
« on: May 30, 2011, 09:37:40 pm »
I just moved from EA 7.1 into EA 9.
I see that functionality "fix up external references" under Get All Latest process is extremely long - about 1 hour or so...

It happen for my crucial (and very big) project with many packages separately configured in version control (SVN).
With version 7.1 it was no problem but now I am in desperation.... come back to 7.1!?  

q2

  • EA Novice
  • *
  • Posts: 19
  • Karma: +0/-0
    • View Profile
Re: Get All Latest is extremely long - EA 9 build
« Reply #1 on: June 02, 2011, 09:44:39 pm »
Finally I resolved it by division... i.e. users load into new eap file not all branches (from one root package) but only several useful "sub-branches" (each such branch is now in fact separate root/model in project).
I was possible because e.g. branches for business analyst are independent from designers and vice versa.

Anyway problem still exist - i.e. in case of very big model at the end of Get all latest (in fact Scan XMI...) EA transform processor for 1-2 hours into good electric heater  ;)