Gantt view: remove resource assignment?
« on: July 11, 2014, 06:25:45 am »
After having resource assigned to SPEM_Process element in Gantt view I decided to remove this assignment and to put the element back to 'Unassigned' state.
So far - no luck. Is there no such option?

VKN

  • EA User
  • **
  • Posts: 187
  • Karma: +9/-1
    • View Profile
Re: Gantt view: remove resource assignment?
« Reply #1 on: July 11, 2014, 09:28:54 am »
Element | Project Management
Right click on the Resource name then select Delete

Also, View | Tagged Values
Select <unassigned>
« Last Edit: July 11, 2014, 09:30:11 am by VKN »