Book a Demo

Author Topic: BPMN 2.0 Task type Service  (Read 6317 times)

akopp

  • EA Novice
  • *
  • Posts: 3
  • Karma: +0/-0
    • View Profile
BPMN 2.0 Task type Service
« on: January 20, 2015, 08:11:40 pm »
In rel 11 new activities added can not be changed to task type service as the task type drop down list doesn´t this type.

Has somebody else the same experience.

Since we need to show this activity type in our diagrams, who knows a workaround.

Eve

  • EA Administrator
  • EA Guru
  • *****
  • Posts: 8110
  • Karma: +119/-20
    • View Profile
Re: BPMN 2.0 Task type Service
« Reply #1 on: January 21, 2015, 08:27:30 am »
If you were previously able to do it, you can still do it by opening the tagged values docked window.

PS. I don't know if what you're wanting is an actual BPMN type. If it is, then it sounds like it may have been omitted and needs to be corrected.

MMA

  • EA User
  • **
  • Posts: 63
  • Karma: +3/-0
    • View Profile
Re: BPMN 2.0 Task type Service
« Reply #2 on: January 21, 2015, 10:53:44 am »
Hi akopp,

You could find "Service" in 3 ways.

1. Quick menu when dropping Activity on diagram, select "Service";
2. Property Window | BPMN2.0 page | Type combobox | select "serviceTask";
3. View | Tag Values | taskType | select "Service"

Hope that helps ;)

Stoppy

  • EA User
  • **
  • Posts: 115
  • Karma: +0/-0
    • View Profile
Re: BPMN 2.0 Task type Service
« Reply #3 on: January 21, 2015, 11:44:30 am »
Hi akopp,

MMA has covered of the functional steps.

I am on EA V 11.0.1105 and not experiencing your issue, could you supply more context to your problem.

Regards,

Stoppy  :D
« Last Edit: January 21, 2015, 11:45:15 am by Stoppy »
Skills: Business Process | Business Analysts | Product Configuration Manager | Business Intelligence

akopp

  • EA Novice
  • *
  • Posts: 3
  • Karma: +0/-0
    • View Profile
Re: BPMN 2.0 Task type Service
« Reply #4 on: January 21, 2015, 09:00:38 pm »
MMA and the others,

Thanks. I am now able to change activities to a service tzpe.

Regards
Andre