Simulation & BPMN Gateway
« on: May 11, 2012, 06:17:11 pm »
Hi,

I am trying to simulate a BPMN process diagram from the example project (Analysis & Business Models / Process Diagrams / Sub Process Activity) and it works great until it gets to a Gateway node.

How do I get the simulation to choose one path over the other?

The examples are not clear OR I am blind.

Thanks,
-Timothy

Tim Twe

  • EA User
  • **
  • Posts: 40
  • Karma: +0/-0
    • View Profile
Re: Simulation & BPMN Gateway
« Reply #1 on: May 12, 2012, 01:44:15 am »
I cannot seem to assign one path (or the other) a "trigger".

Any advice/insight would help greatly.

Sequence diagrams and state diagrams work perfectly.  UML Activity diagrams seem to fail aswell.  I'd expect to see the [constraint] as the highlighted trigger in the Waiting Triggers section.

Paolo F Cantoni

  • EA Guru
  • *****
  • Posts: 8626
  • Karma: +259/-129
  • Inconsistently correct systems DON'T EXIST!
    • View Profile
Re: Simulation & BPMN Gateway
« Reply #2 on: May 14, 2012, 03:31:32 pm »
Hi Tim,

it's the ControlFlow (SequenceFlow) that determines the exit of the Gateway.

Make sure your constraint is implemented as the correct "pseudocode" in the ConditionExpression for the ConditionType "Expression".