General Board / Re: BPSim getting started help
« on: August 03, 2021, 05:03:53 am »
So far the main issue I'm having is not being able to find the option to provide a quantity for the amount of Resources available. I can specify how many are required by an activity but no where to put how many available to calculate a Degree of Utilization.
Other issue, when choosing a Selection for a Resource Parameter, I can add by Resource, I can't figure out what type of element needs to exist in the Simulation package in order to add not by Resource but by Role and adjust their availability.
Lastly, I'm trying to create a Property such as "Number of Issues" and then have the activities I'm modeling take a variable amount of time depending on how many issues. For example, if we are running a process A and it has 12 issues, I want to be able to use a distribution based off historical data to determine how long each issue takes to solve, and then have the activity work through each issue before proceeding.
for example, each issue takes 5-15 minutes, there are 12 issues, I want the activity time to be = {#ofissues} x {time per issue}
Thanks in advance,
John Gara
Other issue, when choosing a Selection for a Resource Parameter, I can add by Resource, I can't figure out what type of element needs to exist in the Simulation package in order to add not by Resource but by Role and adjust their availability.
Lastly, I'm trying to create a Property such as "Number of Issues" and then have the activities I'm modeling take a variable amount of time depending on how many issues. For example, if we are running a process A and it has 12 issues, I want to be able to use a distribution based off historical data to determine how long each issue takes to solve, and then have the activity work through each issue before proceeding.
for example, each issue takes 5-15 minutes, there are 12 issues, I want the activity time to be = {#ofissues} x {time per issue}
Thanks in advance,
John Gara