Author Topic: Reporting in Project Issues  (Read 2406 times)

EA_Nj

  • EA User
  • **
  • Posts: 48
  • Karma: +0/-0
    • View Profile
Reporting in Project Issues
« on: August 08, 2002, 08:19:38 am »
I want to generate reports of Project Issues. However current I have no way of limiting my reports to a particular date or even the project status.

If I need to send multiple reports during a given day this could be a significant problem.

Can you create a filtering mechanism which would allow me to generate reports for selected issues, date-based reports, status based reports?

This would be very very helpful!

Jamal

EA_Nj

  • EA User
  • **
  • Posts: 48
  • Karma: +0/-0
    • View Profile
Re: Reporting in Project Issues
« Reply #1 on: August 08, 2002, 12:04:35 pm »
Another thing that I've noticed is that when the report is printed there is no proper sorting of the issues. It's all haphazard.  Can you put in the sorting capability so that if I want the report to be sorted by date, issue stats (Open, Under review etc.) i could do it?

My users are having a very tough time reading these reports!

Thanks,