Configure Timeline - States

You can manage states using the 'States' tab of the 'Configure Timeline' dialog. To display this dialog, either:

  • Double-click on the Lifeline element
  • Right-click on the Lifeline element and select the 'Properties' option, or
  • On a Value Lifeline, click on the Edit State Lifeline button

The 'Configure Timeline' dialog defaults to the 'States' tab.

All states currently defined for the Lifeline element are listed in the 'States' panel.

Add a new State

Step

Action

1

In the 'State Name' field, type the name of the first new state in the Lifeline element; for example, 'WaitState'.

2

Click on the Save button.

The state is added to the 'States' panel and (for a State Lifeline Element) to the diagram.

3

Click on the New button.

4

In the 'State Name' field, type the name of the next state in the Lifeline element.

5

Repeat steps 2 to 5 until you have added all required states (you must add at least three to the Lifeline element).

6

When you have added all the required states, click on the OK button to close the 'Configure Timeline' dialog.

Edit an existing state

Step

Action

1

Click on the state in the 'States:' list.

2

In the 'State Name' field, change the name of the state.

3

Click on the Save button.

Delete an existing State

Step

Action

1

Click on the state in the 'States:' list.

2

Click on the Delete button.

Change the order of States

Step

Action

1

Click on the state in the 'States:' list.

2

Click on the Up or Down icon buttons to move the state up or down the sequence.