How do I remove an aborted Get All Latest lock?
« on: July 13, 2010, 06:19:59 pm »
Okay we have a situation whereby an attempt to abort a Get All Latest has been performed by killing EA client using Windows Task Manager.

We are using EA 8.858, MySQL for EA repository and ClearCase for version control.

The process was abandoned due to the wrong ClearCase config. spec. being used for the Get All Latest. This would have loaded the wrong information into the team model.

Any action now reports that the Get All Latest must be completed before we can continue, however, even a Get All Latest with the correct config.spec. will not run.

None of the XML files are locked under ClearCase, EA alone must be keeping tabs of this in the repository.

Does anyone know how to remove this lock so that a Get All Latest can be performed using the correct ClearCase configuration?

I have tried a Re-synch All Packages to no avail.

pH

  • EA User
  • **
  • Posts: 72
  • Karma: +0/-0
    • View Profile
Re: How do I remove an aborted Get All Latest lock
« Reply #1 on: July 13, 2010, 06:26:26 pm »
Get the lock manually on xml files. Then do Re-Synch Status with VC Provider. Then you can try Check In Branch or individually undo checkout.

HTH,
pH